INSTALLATION OF PU HAD TO BE PUT ON HOLD
Plaats

Lokeren

Type uitgevoerde werken

Installation of PU had to be put on hold due to a very wet substrate

For the proper installation of PU flooring, you need to have a dry, dust-free substrate and the minimum temperature of the floor surface has to be 5°C. If the surface onto which the PU is sprayed is not dry, the water will generate a very intense chemical reaction in the polyurethane foam, resulting in a high risk that depressions will form!

In order to get the concrete substrate in this building nice and dry, in this case, a gold package was used, consisting of 2 DF400 industrial dehumidifiers, 2 DFE25 electric heaters and 2 powerful TTV4500 fans.

NAAR OVERZICHT
Discover our tips

Building dryer: water damage
Using a building dryer is essential when your home has fallen prey to water damage. If you fail to do so, the consequences can be serious.
Read more >

Discover all our tips
Discover our tips

Laying parquet
Your building project is finally coming to an end. Are you planning to install parquet flooring? Then make sure that the screed has fully dried out.
Read more >

Discover all our tips
Discover our tips

Types of building dryers
In principle, there are two types of dryers on the market: condensation dryers and adsorption dryers. For drying out buildings we always use condensation dryers.
Read more >

Discover all our tips
Discover our tips

Painting after drying
The plastering phase of your project is almost completed. Now is the time for efficient drying of the plasterwork. One address: Buildingdryers.be!
Read more >

Discover all our tips
Discover our tips

Odour control
Are you suffering from air pollution in your home or business? Ozone generators allow odour components and other air pollutants to be efficiently decomposed at molecular level.
Read more >

Discover all our tips